Rebar Calculator

Work out the bars a slab mat takes both ways, with the cover, the splices and the stock length all accounted for.

The slab

The slab

The finished slab, measured on the ground. An L shape is easier as two rectangles worked out separately and added together.
In feet. Both measurements are the slab itself, not the formwork or the excavation.

The mat

Read it off the drawing. A mat is usually specified as a bar size at a spacing, written like "#4 at 18 in o.c. each way". This calculator uses the same spacing in both directions, which is the common case.
The bar number is its diameter in eighths of an inch, so a #4 is half an inch. The size does not change how many bars you need, only how long each splice has to be, since laps are specified as a multiple of the diameter.
How far in from the edge of the slab the outermost bar sits. It shortens every bar and narrows the span the bars are spaced across, so it changes the count as well as the lengths. Three inches is the usual figure for concrete cast against the ground; take it from the drawing where there is one.
ACI 318 makes the lap depend on bar size, concrete strength, cover, spacing and coating, so there is no single correct multiplier and the drawings or the engineer settle it. Forty diameters is commonly specified and is set here so the answer is complete out of the box. Set it to zero to see the bar lengths with no splice allowance at all.

What you are buying

Twenty feet is the common stock length, with 10 ft also widely carried and 40 and 60 ft available on order. It decides both how many sticks you buy and how many splices the mat needs, since any run longer than one stick has to be lapped.
The price of one bar at the stock length above. Rebar is sometimes quoted by weight instead, in which case multiply the price per pound by the weight of one stick.
Five percent covers the offcuts on a plain rectangle, where most bars run full length. Allow more on a slab with a lot of edges, blockouts or thickenings, because every one of those ends a bar early and the short piece rarely finds a home. 5.00%
The order
17 stock bars
Bars running lengthwise 8 bars
Bars running widthwise 14 bars
Total bar length 317 ft
Crossings to tie 112 ties
Slab area
240 sq ft
Waste
5.00%

The detail

Bar run, lengthwise 19.5 ft
Bar run, widthwise 11.5 ft
Bar length before laps 317 ft
Splices 0 laps
Each lap 20 in
Added by the laps 0 ft
Material cost $0
Cost per square foot $0.00

Every figure here is a planning estimate, not a professional takeoff. Yields, waste factors and code requirements vary by product, supplier and jurisdiction, so confirm quantities against the manufacturer’s data and your local building department before you order.

Generated by Mathterial

A reinforcing mat is bars running both ways at a spacing, and the thing that catches people is that the count is fenceposts rather than fence panels. A 12 foot span at 18 inch centers takes nine bars, not eight. This rebar calculator does both directions, takes the concrete cover off the ends, works out where the splices fall against your stock length, and tells you how many bars to buy.

Bars at a spacing are fenceposts

Divide the span by the spacing and you have counted the gaps, not the bars. There is always one more bar than there are gaps, because the mat has to be closed at both edges.

It is a small error on one run and a large one on a mat, because it happens in both directions at once. On a 20 by 12 foot slab at 18 inch centers it is two bars missing out of twenty-two, and they are the two along the edges, which are the ones you notice.

Concrete cover changes the count, not just the length

Cover is the depth of concrete between the steel and the face of the slab, and it is what keeps water and fire off the bar. Three inches is the usual figure where concrete is cast against the ground.

Most calculators treat it as a trim on the bar lengths. It is more than that: pulling the mat in from both edges narrows the span the bars are spread across, so it can drop a whole bar out of each direction. The calculator above applies it both ways, and the detail panel shows the two runs it ends up with so you can see what it did.

The lap is yours to set, and that is the point

Every other rebar calculator we have seen quietly assumes a lap splice of 40 bar diameters and never mentions it. That figure is commonly specified and it is a reasonable place to start, which is why it is pre-filled here. It is not a code requirement.

ACI 318 makes the required lap depend on the bar size, the concrete strength, the cover, the spacing between bars, whether the bar is epoxy coated and whether it sits near the top of a deep pour. Those conditions move the answer in both directions. There is no single multiplier that is right for every slab, so the field is exposed rather than buried, and the number that belongs in it is the one on your drawings.

Set it to zero and you get the bar lengths with no splice allowance at all, which is a useful sanity check against a quote.

Stock length decides how many splices you have

Twenty feet is the common stock length, with 10 feet widely carried and 40 and 60 available on order. Any run longer than one stick has to be lapped, and every lap adds its own overlap to the total.

This is where the arithmetic turns on itself. A 20 foot slab on 20 foot bars has no splices in the long direction at all. Stretch it to 21 feet and every single lengthwise bar suddenly needs a splice, and each of those splices eats another lap. The jump is real and the calculator shows it, so it is worth trying your slab against two stock lengths before ordering.

Tie wire

The crossings figure is every intersection in the mat, which is the upper bound on ties. Tie wire holds the bars in position while the concrete goes in and carries no load afterwards, so not every crossing is always tied, and a job that ties every other one halves that number.

What this is not

This is a quantity takeoff, not a design. It tells you how much steel a mat at a given size and spacing comes to. It does not tell you what size or spacing your slab needs, and nothing here should be read as saying a mat is adequate for a load.

The bar size, the spacing, the cover and the lap all come from a drawing or an engineer. Bring those four numbers here and this will price and order them for you.